The Study is scheduled to begin towards the end of 2011 and proceed through February, 2014.  Please see below for a tentative project schedule.  This schedule will be routinely updated as more detailed scheduling information becomes available.

 

Project Tasks

Refine Study Goals and Scope ............................................. .November, 2011

Public Outreach .....................................................................Ongoing

Municipal Advisory Group (MAG) Meeting .................August, 22, 2012

Focus Group Meetings/Workshops (3).........................October, 2012 - January, 2013

Existing Conditions Report .....................................................June, 2013

Selection of 3 Station Areas ...................................................June, 2013

Public Workshops .................................................................October - November, 2013

Final Feasibility Report ..........................................................January - February, 2014

Total Project Duration........................................................24-27 months

 

 